PMP Certification is considered to be the golden standard in the field of project management. It would be attracted towards many experienced professionals who desire to for advancing their career by a notch. Here we would be discussing obtaining sample questions from PMP Certification Question Papers. For more details, you could refer to SPOTO PMP Exam Dumps to achieve success in your very first attempt. It would provide give you a better picture of why obtaining PMP certification would matter so much.
PMP Certification Question Papers:
1. Delineate Project Scope.
a. It is considered to be the design of experiments that would be utilized to complete the project work.
b. It is considered to be the combination of the cost as well as the schedule which would be required for completing the project work.
c. It is considered as the description of the required work that would be necessary for completing the project. [Ans]
d. It is considered as the description of the required work as well as resources that would be required for completing the project.
2. Define Program
a. A very complex and large project.
b. A collection of projects which would be consisting of common resources. [Ans]
c. A collection of sub-projects that would possess a common goal.
d. A collection of subprojects that would possess a common customer.
3. Which of the following would be comprising the Project Life Cycle?
a. Activities
b. Estimates
c. Milestones
d. Phases [Ans]
4. Being the project manager of the ABC Project, you would have allowed subsequent project phases for beginning even before the phase of predecessor completes. Which of the following would be relating to this scenario?
a. Crashing
b. Fast-tracking [Ans]
c. Risk management
d. Tandem scheduling
5. The person or group who would be offering the support and resources for the project, portfolio, or program and is also considered to be responsible for enabling success is called the:
a. Project Manager
b. Senior Management
c. Sponsor [Ans]
d. Client
6. Which of the following couldn’t be the part of techniques of Group creativity:
a. Affinity Diagram
b. Brainstorming
c. Nominal Group Technique
d. Vendor Bid Analysis [Ans]
7. Being the project manager of a thermal power plant project you are required for managing the construction of an administrative unit building. Which of the following technique would you use to quickly for estimating and decide the utilization of historic experts and estimate judgment?
a. Analogous Estimating [Ans]
b. Parametric Estimating
c. Historical Estimating
d. Expert Judgement
8. What would be an acceptable range utilized for determining the realistic activity cost estimates?
a. Cost Management Plan
b. Level of Accuracy [Ans]
c. Level of Precision
d. Units of Measure
Here are some of the questions, from the PMP Certification Question Paper, check out the SPOTO PMP Exam Dumps to achieve success in your very first attempt. When it comes to PMP Exam, SPOTO PMP Exam Dumps, are considered to be the best that you could obtain.